How many dock doors do you need?

Too few doors and trucks wait in the yard. Too many and you pay for space you don't use. Here is a simple way to work it out from three numbers you already know.

By Yauheni Pachka, founder of SimpleDocks
Updated

In short

  • You need three numbers: trucks per day, average time at a door, and the hours you take trucks.
  • Door-hours needed = trucks per day × hours each truck is at the door.
  • Doors = door-hours needed ÷ hours open, then add room for peaks and trailers parked at doors.
  • Booked arrival times let the same number of doors handle more trucks.

The simple math

Worked example (example numbers only)
StepExample
Trucks per day24
Average time at the door1.5 hours
Door-hours needed24 × 1.5 = 36
Hours you take trucks10
Doors if trucks were spread evenly36 ÷ 10 = 3.6, so 4
Add room for peaks (about a third)4 + 2 = 6 doors

Trucks rarely arrive evenly. Most small docks see bunches at opening and after lunch, which is why the extra room matters.

What changes the answer

  • Arrival peaks. If half your trucks come in the first two hours, you need doors for that rush, not for the daily average.
  • Trailers parked at doors. A trailer being loaded over several hours takes a door the whole time.
  • Live unloads vs drops. A dropped trailer can wait in the yard; a driver waiting for a live unload needs a door now.
  • Your own trucks. Outbound trailers you are loading count too.

Get more out of the doors you have

  • Book arrival times with no more trucks per slot than you have doors.
  • Move finished trailers to the yard so the door is free.
  • Have the job ready before the truck backs in.
  • Watch which doors sit busy for a long time, and why.

How SimpleDocks helps

SimpleDocks' booking page only offers open times, with at most one truck per door in a slot. The Dock Wall shows every door, free, busy, finished or out of service, and flags doors that have been busy a long time. Yard trucks can move trailers between the doors and the yard, so finished trailers don't block a door.

Plan booking around your doors.

Read the booking guide

Keep reading

Dock door capacity calculatorHow many trucks your doors can take, and your busiest hour.

Questions

How many trucks can one dock door handle a day?

Divide the hours you take trucks by the average time a truck spends at the door. At 1.5 hours a truck and 10 hours open, about 6 trucks, if they arrive evenly.

How long does it take to unload a truck?

It depends on the freight and how it is loaded. Palletized freight on a full trailer is often unloaded in under an hour; floor-loaded freight takes much longer. Use your own average.

Should I add doors or book times first?

Book times first. Spreading arrivals often frees enough door time to avoid building more doors.

Do I need a door for every trailer I am loading?

Only while it is being loaded. Move it to the yard when it is full, and bring it back when it is time to go.

More from SimpleDocks

Run the warehouse. Stop chasing updates.

Bookings, dock doors, forklift work, storage, your own trucks and the invoice at the end, in one app your team picks up on day one.